Wallonia Orders Google to Halt Work at Contested Charleroi-Area Data Centre
Regional inspectors told Google to stop building a three-hectare data centre at a former mine near Charleroi, saying its amended permit was revoked in August.
How they tell it
10%7 outlets · 7 languages
none critical, 3 neutral, none favorable
Read the divergences
Walloon regional authorities ordered Google on Friday 27 November to suspend construction of a data centre in southern Belgium, saying the company lacked valid planning permission. Nicolas Yernaux, spokesman for the Walloon authorities, told AFP that inspectors had identified "a major offence: the illegal construction of a building covering three hectares". The site is a former mining area of about 50 hectares; according to the Walloon official Raphaël Stokis, cited by 444, the building stands in an industrial park at Aiseau-Presles, roughly 15 kilometres west of Charleroi, and is one of three data centres Google originally planned for the area. Inspectors visited on Thursday to notify Google representatives of the stop-work order, the regional authority said.
According to Stokis, inspectors found the structure almost complete, with structural works finished despite the refusal of the permit; 300 workers on site were verbally instructed to stop, an instruction later confirmed in writing to the company, 444 reported. In a statement cited by 444, Google said it was "committed to maintaining open and cooperative dialogue with the regional authorities". ORF reported that the company did not initially respond, and The Korea Times that it did not immediately answer AFP's request for comment.
Greenpeace Belgium said a report published this week included drone footage showing work continuing after the latest version of the planning permission was revoked in August, and that it had filed an urgent application with local planning authorities. "The tech giant is currently continuing its work, even though in August the latest version of its planning permission to build this data center was revoked," the organisation said, according to The Korea Times. The authorities said Greenpeace had drawn their attention to the case, ORF reported.
The dispute turns on cooling. Google obtained a permit in 2024 for three smaller, air-cooled data centres. It later sought to merge two of them into a single larger facility and to draw up to 600 cubic metres of water an hour from the nearby Sambre for liquid cooling, according to 444. ORF reports that the company applied for a larger building area and Sambre water use in 2026, while 444 dates the amendment request to 2025; the two accounts differ on the year. The regional administration approved the changes in April, but after appeals from residents and campaign groups, François Desquesnes, Wallonia's infrastructure minister, revoked the amended permit in August, citing drought concerns, according to 444. The Korea Times reports that regional officials refused the permit application over the summer.
Google has challenged the revocation before Belgium's Council of State, which is expected to rule on 7 January, according to 444; The Korea Times reports a court hearing scheduled for January. The dispute is the latest Google faces in Europe as technology companies race to build data centres to support artificial intelligence, The Korea Times reports. In October, Finnish authorities ordered work halted at two Google data centre sites in the country until mandatory environmental impact assessments were completed.
The Divergence across 3 points of view
- Critical: no bloc
- Neutral: EUR, GIAPPONE_COREA_TAIWAN, LAT
- Favorable: no bloc
- Pale: the bloc has no reading of this story
Bloc by bloc, from the most critical to the most favourable
EUR Continental European pressNeutral
Reading
Walloon inspectors speak through the record: an illegal three-hectare build, a permission revoked in August, a drought that makes river cooling untenable — and the regulator's side is held against the company's pending appeal.
Description
Walloon inspectors halt a Google data-centre build after finding a three-hectare structure rising without valid permits, following a Greenpeace complaint backed by drone footage. The dispute is anchored in Google's bid to replace air cooling with water from the Sambre during a prolonged drought, and set beside a Finnish stop order from October. The register stays administrative: revoked permits, appeals, a January hearing.
Mechanismproceduralisation
The halt is rendered as the next link in a documented chain — permit, amendment, revocation, inspection — so it reads as the routine outcome of procedure rather than a judgment on the company.
GIAPPONE_COREA_TAIWANNeutral
Reading
An agency voice datelined Brussels lets the Walloon spokesman and Greenpeace carry the accusation, notes that the company did not respond, and keeps to facts and timelines.
Description
One English-language Korean outlet carries an agency-fed account built as a short summary plus bullet key facts: the stop order, three hectares inside a 50-hectare former mine, a water-cooling amendment refused over drought, a January hearing. Context reaches the AI-driven data-centre race and an October Finnish order. The bloc picture rests on a single sampled outlet and is thin.
Mechanismfact-sheet compression
The material is compressed into a summary block and enumerated key facts, which foregrounds checkable items and pushes evaluation out of the text.
LAT Latin American pressNeutral
Reading
A regional official's statement leads, the environmental complaint follows as the trigger, and the company gets only its right of appeal — the account stands with the permitting authority.
Description
A wire-derived account in Central American Spanish opens with the regional spokesman confirming the halt, credits Greenpeace drone footage for triggering the inspection, and centres the fight on Sambre water during drought. It closes by widening to Google's European legal fronts and Finland's October order. The register is flat and declarative.
Mechanismattribution sequencing
Attribution is stacked in order — official confirmation, NGO evidence, company recourse — so the balance is produced by sequencing rather than by evaluating claims.
This story appeared in
🇦🇹Austria1
🇨🇷Costa Rica1
🇪🇪Estonia1
🇭🇺Hungary1
🇮🇹Italy1
🇰🇷South Korea1
🇸🇰Slovakia1
On the same topic
Broaden your view
Wallonia Orders Google to Halt Work at Contested Charleroi-Area Data Centre
Regional inspectors told Google to stop building a three-hectare data centre at a former mine near Charleroi, saying its amended permit was revoked in August.

Walloon regional authorities ordered Google on Friday 27 November to suspend construction of a data centre in southern Belgium, saying the company lacked valid planning permission. Nicolas Yernaux, spokesman for the Walloon authorities, told AFP that inspectors had identified "a major offence: the illegal construction of a building covering three hectares". The site is a former mining area of about 50 hectares; according to the Walloon official Raphaël Stokis, cited by 444, the building stands in an industrial park at Aiseau-Presles, roughly 15 kilometres west of Charleroi, and is one of three data centres Google originally planned for the area. Inspectors visited on Thursday to notify Google representatives of the stop-work order, the regional authority said.
According to Stokis, inspectors found the structure almost complete, with structural works finished despite the refusal of the permit; 300 workers on site were verbally instructed to stop, an instruction later confirmed in writing to the company, 444 reported. In a statement cited by 444, Google said it was "committed to maintaining open and cooperative dialogue with the regional authorities". ORF reported that the company did not initially respond, and The Korea Times that it did not immediately answer AFP's request for comment.
Greenpeace Belgium said a report published this week included drone footage showing work continuing after the latest version of the planning permission was revoked in August, and that it had filed an urgent application with local planning authorities. "The tech giant is currently continuing its work, even though in August the latest version of its planning permission to build this data center was revoked," the organisation said, according to The Korea Times. The authorities said Greenpeace had drawn their attention to the case, ORF reported.
The dispute turns on cooling. Google obtained a permit in 2024 for three smaller, air-cooled data centres. It later sought to merge two of them into a single larger facility and to draw up to 600 cubic metres of water an hour from the nearby Sambre for liquid cooling, according to 444. ORF reports that the company applied for a larger building area and Sambre water use in 2026, while 444 dates the amendment request to 2025; the two accounts differ on the year. The regional administration approved the changes in April, but after appeals from residents and campaign groups, François Desquesnes, Wallonia's infrastructure minister, revoked the amended permit in August, citing drought concerns, according to 444. The Korea Times reports that regional officials refused the permit application over the summer.
Google has challenged the revocation before Belgium's Council of State, which is expected to rule on 7 January, according to 444; The Korea Times reports a court hearing scheduled for January. The dispute is the latest Google faces in Europe as technology companies race to build data centres to support artificial intelligence, The Korea Times reports. In October, Finnish authorities ordered work halted at two Google data centre sites in the country until mandatory environmental impact assessments were completed.
The Divergence across 3 points of view
- Critical: no bloc
- Neutral: EUR, GIAPPONE_COREA_TAIWAN, LAT
- Favorable: no bloc
- Pale: the bloc has no reading of this story
EUR Continental European pressNeutral
Reading
Walloon inspectors speak through the record: an illegal three-hectare build, a permission revoked in August, a drought that makes river cooling untenable — and the regulator's side is held against the company's pending appeal.
Description
Walloon inspectors halt a Google data-centre build after finding a three-hectare structure rising without valid permits, following a Greenpeace complaint backed by drone footage. The dispute is anchored in Google's bid to replace air cooling with water from the Sambre during a prolonged drought, and set beside a Finnish stop order from October. The register stays administrative: revoked permits, appeals, a January hearing.
Mechanismproceduralisation
The halt is rendered as the next link in a documented chain — permit, amendment, revocation, inspection — so it reads as the routine outcome of procedure rather than a judgment on the company.
Bloc by bloc, from the most critical to the most favourable
EUR Continental European pressNeutral
Reading
Walloon inspectors speak through the record: an illegal three-hectare build, a permission revoked in August, a drought that makes river cooling untenable — and the regulator's side is held against the company's pending appeal.
Description
Walloon inspectors halt a Google data-centre build after finding a three-hectare structure rising without valid permits, following a Greenpeace complaint backed by drone footage. The dispute is anchored in Google's bid to replace air cooling with water from the Sambre during a prolonged drought, and set beside a Finnish stop order from October. The register stays administrative: revoked permits, appeals, a January hearing.
Mechanismproceduralisation
The halt is rendered as the next link in a documented chain — permit, amendment, revocation, inspection — so it reads as the routine outcome of procedure rather than a judgment on the company.
GIAPPONE_COREA_TAIWANNeutral
Reading
An agency voice datelined Brussels lets the Walloon spokesman and Greenpeace carry the accusation, notes that the company did not respond, and keeps to facts and timelines.
Description
One English-language Korean outlet carries an agency-fed account built as a short summary plus bullet key facts: the stop order, three hectares inside a 50-hectare former mine, a water-cooling amendment refused over drought, a January hearing. Context reaches the AI-driven data-centre race and an October Finnish order. The bloc picture rests on a single sampled outlet and is thin.
Mechanismfact-sheet compression
The material is compressed into a summary block and enumerated key facts, which foregrounds checkable items and pushes evaluation out of the text.
LAT Latin American pressNeutral
Reading
A regional official's statement leads, the environmental complaint follows as the trigger, and the company gets only its right of appeal — the account stands with the permitting authority.
Description
A wire-derived account in Central American Spanish opens with the regional spokesman confirming the halt, credits Greenpeace drone footage for triggering the inspection, and centres the fight on Sambre water during drought. It closes by widening to Google's European legal fronts and Finland's October order. The register is flat and declarative.
Mechanismattribution sequencing
Attribution is stacked in order — official confirmation, NGO evidence, company recourse — so the balance is produced by sequencing rather than by evaluating claims.